Clearing Trees
 Clearing trees and making new roads to access the new Flint Township Police Department.
|
Future Site Of The Flint Twp. Police Department
 5200 Norko Drive is the address of the new police facility soon to be built.
Picture Date: 2/21/2002
|
Site Of New Building
 5200 Norko Road is the address to the soon to be new Flint Township Police Department. The new facility will be at the corners of Norko and Fleckenstein Drives
|
Contruction Trailer

|
O'Neal Drive
 O'Neal Drive is nearing completion. The road is curbed and ready to be paved.
Picture Date: 6/10/2002
|
Overview Of Site
 The trees are gettin cleared and contruction is starting to begin.
Picture Date: 7/4/2002
|
O'Neal Drive
 O'Neal Drive
O'Neal and Menoutes Drives get the first layer of pavement.
Picture Date: 7/5/2002
|
Basement Forms
 The basement is dug out and foundation poured. These forms will soon be filled with concrete and the basement walls will begin.
Picture Date: 8/17/2002
|
Basement Forms
 This view is looking across the basement forms that will soon hold the new basement walls. This veiw is looking west across the new building.
Picture Date: 8/17/2002
|
Basement
 This will soon be a busy police department. The building will have two levels, main floor and basement. This will soon be the basement walls and floor.
Picture Date: 8/17/2002
|
Basement Walls
 The concrete has been poured and the forms removed. The concrete basement walls now appear.
Picture Date: 10/9/2002
|
Site Overview From Above
 The contruction site is busy with activity. The construction workers are getting the site ready for the steel strutures that will be delivered soon.
Picture Date: 10/14/2002
|
Township's First Park
 To the west of the new polce building is wooded land. The township owns the land all the way to Dye Road. The township wants to develop that land in it's first park.
Picture Date: 10/14/2002
|
Steel Structure
 The new newly delivered steel makes it look like a building.
Picture Date: 10/20/2002
|
Basement
 Basement
The basement will hold the Sgt. offices, roll call, training areas, and locker rooms.
Picture Date: 10/20/2002
|
Employee Parking
 The employee parking area has been leveled and is ready to have the curbs set.
Picture Date: 10/20/2002
|
Rear Of The Building
 The rear of the building will be employee parking and a security garage.
Picture Date: 11/3/2002
|
Employee Drive
 This is the drive going out to O'Neal and Menoutes.
Picture Date: 11/3/2002
|
Employee Parking Lot
 This will be employee parking, deparment vehicle parking, and access to the security garage.
Picture Date: 11/3/2002
|
New Construction Sign
 The new construction sign is up at the site.
Picture Date: 11/26/2002
|
East End Of The Building
 The east end of the building.
Picture Date: 11/26/2002
|
Parking Lot
 The parking lot has the first layer of asphalt.
Picture Date: 11/26/2002
|
Front Of Building
 The front center of the building.
Picture Date: 12/8/2002
|
Inside The Building
 This area will be the adminstative offices. The far end is the main entrance.
Picture Date: 12/8/2002
|
Sgt. Offices
 These offices are the sgt. offices in the lower level of the building.
Picture Date: 12/8/2002
|
Rear Of Building
 The brick walls are being layed under the plastic wrap.
Picture Date: 1/8/2003
|
Entrance Lobby
 The main entrance is here into the lobby.
Picture Date: 1/8/2003
|
Finished West Wall
 This is the finished brick on the west wall.
Picture Date: 1/8/2003
|
Roll Call Room
 At the begining of each shift the offices meet with a supervisor to get their assignments. This will be the roll call room.
Picture Date: 1/8/2003
|
Site From Norko Road
 It's cold out, but the work continues on the new building.
Picture Date: 1/28/2003
|
West Outside Wall
 This is the west outside wall. The brick is on the wall and windows won't be far.
Picture Date: 2/9/2003
|
Middle Of Main Floor
 A lot of work needs to be done before it will look like a police station.
Picture Date: 1/28/2003
|
Electrical Room
 Electrical Room
I hope someone took notes. Anyone knows where this wire goes?
Picture Date: 1/28/2003
|
West Outside Wall
 This is the west outside wall. The brick is on the wall and windows won't be far.
Picture Date: 2/9/2003
|
Main Floor
 The main floor will not look like this long.
Picture Date: 2/9/2003
|
Holding Cells Layout
 The holding cells will soon be built. The bricks on the floor is the layout of the cells.
Picture Date: 2/9/2003
|
Windows
 Windows are finnaly going in. This is the back west side of the building and has the first windows in.
Picture Date: 2/19/2003
|
Basement
 This is the roll call room. The room to the left will be the officers report room. The room to the right will be a sgt's office.
Picture Date: 2/19/2003
|
Cell Windows
 The windows are to a holding cell. The cells will be constructed of brick, steel, and unbreakable glass.
Picture Date: 2/19/2003
|
Front Brick And Window Ledge
 The brick looks good.
Picture Date: 2/28/2003
|
Sally Port
 This is the back wall of he sally port. The sally port is basically garage the officers can drive into and close the door before letting the prisonner out. A sally port is for safety of the officers and community.
Picture Date: 2/28/2003
|
Stud Walls
 The steel studs are being put in upstairs. It is a maze at this point with all the openings.
Picture Date: 2/28/2003
|
Drunk Tank
 This will be the drunk tank. The cells will wrap around dispatch where the prisonners will be watched by a person and CCTV.
Picture Date: 2/28/2003
|
Community Center
 The community center is on the east side of the building. It's a little airy still.
Picture Date: 3/9/2003
|
Chief's Office
 This is the chief's office looking back to the back of the building.
Picture Date: 3/9/2003
|
Lobby
 The door on the far side will be the main front door. This will be the lobby.
Picture Date: 3/9/2003
|
Sky Light
 The sky light is in the lobby.
Picture Date: 3/9/2003
|
Sally Port
 The garage on the rear is a sally port for loading and unloading prisonners.
Picture Date: 3/28/2003
|
Holding Cells
 The cells are made out of cement blocks and steel for security.
Picture Date: 3/28/2003
|
Booking Room
 This will be the booking room. The room in the back is an interview room and the bars on the wall are to secure prisonners to.
Picture Date: 3/28/2003
|
Front Of Building
 The community room is now being added to the right side of the building.
Picture Date: 5/1/2003
|
Rear Of The Building
 The back of the building has the sally port attached. Starting to look like a building.
Picture Date: 5/1/2003
|
Detective's Office
 This will be the detective bureau. The office in the back will be the DB Sgt.
Picture Date: 5/1/2003
|
Lobby
 This is the main lobby. There will be a desk at the end.
Picture Date: 5/1/2003
|
Community Center
 This is the community center.
Picture Date: 5/16/2003
|
Dispatch Center
 This will be the dispatch center. The holding cells are beyond the glass windows.
Picture Date: 5/16/2003
|
Holding Cell
 This is the largest of the holding cells.
Picture Date: 5/16/2003
|
Women's Locker Room
 The tile are going in the women's locker room.
Picture Date: 5/16/2003
|
Front Windows
 The front wall of the building.
Picture Date: 5/23/2003
|
Front Parking Lot
 This will be the front parking lot and stairway to the front doors.
Picture Date: 5/23/2003
|
Downstairs Front Hall
 This is the downstairs front hallway.
Picture Date: 5/23/2003
|
Roll Call Room
 This the roll call room. The office begin their shift here. The supervisor will give them their shift assignments and any updates needed.
Picture Date: 5/23/2003
|
Front Of Building
 Picture Date: 7/8/2003
|
Community Center Doors

|
Holding Cell
 The holding cell has just been painted. The concrete bench looks cozy.
Picture Date: 7/8/2003
|
Break Room
 The employee lounge has the cabinets going in.
Picture Date: 7/8/2003
|
Front Of The Police Department
 This is the front and the public entrance to the new department.
Picture Date: 9/2/2003
|
Police Lights
 On each side of the front entrance are blue police lights.
Picture Date: 9/2/2003
|
Sally Port
 This is the sally port where the officers will bring in prisoneers.s
Picture Date: 9/2/2003
|
Front Lobby
 This is the front public lobby.
Picture Date: 9/2/2003
|
Reception Area
 The receptionist will be behind this desk to assist the public.
Picture Date: 9/2/2003
|
Dispatch Center
 The desk is for dispatch. To the left and rear of the picture are the holding cell.
Picture Date: 9/2/2003
|
The Community Room
 The community room is on the east side of the building.
Picture Date: 9/2/2003
|
Detective Bureau
 The detective's will be in this area
Picture Date: 9/2/2003
|
Holding Cell
 One of the holding cells
Picture Date: 9/2/2003
|
Holding Cell
 Another holding cell
Picture Date: 9/2/2003
|
Large Holding Tank
 The holding cells are smaller cells. The holding tank is a larger tank that holds multiple people.
Picture Date: 9/2/2003
|
Booking Desk
 This is the booking desk. The prisoneers will be processed in this room which includes fingerprints and pictures.
Picture Date: 9/2/2003
|
Labratory

|
Work Out Room
 The work out for the officers.
Picture Date: 9/2/2003
|
Sgt. Offices
 Picture Date: 9/2/2003
|
Roll Call Room
 The roll call room is where the officers meet with a sgt. to recieve their assignments for the day.
Picture Date: 9/2/2003
|
Front Hall
 Picture Date: 9/2/2003
|
Evidence Lockers
 Evidence and property will be locked in the loockers.
Picture Date: 9/2/2003
|
Evidence Locker Rear
 The evidence room tech will take the property from the lockers from the rear. It will then get put in it's proper place.
Picture Date: 9/2/2003
|
Equipment Room
 The equipment room will hold walkie-talkies, cameras, PBT's, flashlights, and firearms that the officers check out each day.
Picture Date: 9/2/2003
|
Front Of Building Far
 Picture Date: 9/30/2003
|
Front Of Building From The Flag Poles
 Picture Date: 9/30/2003
|
Front Stairs
 Looking up the stairs at the front doors.
Picture Date: 9/30/2003
|
East Side Of The Building
 This is the community center side.
Picture Date: 9/30/2003
|
Sally Port Doors
 Picture Date: 9/30/2003
|
Dispatch Center
 Picture Date: 9/30/2003
|
Drunk Tank
 Picture Date: 9/30/2003
|
The Main Lobby
 Picture Date: 9/30/2003
|
Communtiy Center
 Picture Date: 9/30/2003
|
Staff Gym
 Picture Date: 9/30/2003
|
The Men's Locker Room
 Picture Date: 9/30/2003
|
The Roll Call Room
 Picture Date: 9/30/2003
|
Sgt. Offices
 Date: 9/30/2003
|
A Lab For Processing Crime Scenes
 Picture Date: 9/30/2003
|
| |